Start Date: February 1, 2021 at 8:00 AM
End Date: May 31, 2021 at 8:00 PM
The Fallowfield Village Cable Renewal Project is being completed as an essential requirement to replace both the overhead and underground equipment to maintain the electricity capacity required to provide power to the Rideau-Goulbourn ward.
What will this project include
- Excavation and replacement of 4 existing poles
- Removal and replacement of 11 transformers located on impacted streets
- Excavation and replacement of underground cables located in this area
Why we are moving forward with this project
Hydro Ottawa equipment located in this area is reaching end of life. As a result, it is essential to replace this equipment to ensure the overall reliability of the electricity distribution system in the area moving forward.
If you missed it
In case you weren't able to attend the virtual Open House for the Fallowfield project on January 11 and 12, below are some of the top questions and answers.
hydroottawa.com/FallowfieldVillage/FAQ
hydroottawa.com/FallowfieldVillage/TopQuestions
System Designer / Project Manager
If you still have questions about your specific property, please contact John Sodja at [email protected]