Pole Renewal Project - Thunder Road - Phase 2

Start Date:
End Date:

Hydro Ottawa is investing in your neighbourhood to safely deliver the highest level of customer service.  

Electricity distribution assets have a lifespan of 50 years or less, Hydro Ottawa regularly replaces and upgrades its infrastructure servicing our community in order to stay ahead of this aging curve.  As such, this project will involve the installation of poles, overhead primary and secondary conductors, as well as the relocation of existing equipment to maintain a reliable service to the Osgoode ward. 

Starting on May 24, 2021 Hydro Ottawa will be working along Thunder Road (between Anderson Road and Ramsayville Road). This project has an estimated completion date of September 24, 2021

Overall, this work includes:

  • The replacement and installation of aging poles and equipment located on the above streets;
  • Installation of overhead primary and secondary conductors;
  • Maintaining overhead and underground cables to service homes; and
  • Tree trimming where required.

Planned power outages will be necessary in order to complete this work. As a result, power outages of 8-10 hours will impact 10-12 customers each time. Timing on this phase of the project will be communicated to you and all impacted customers ahead of time, once confirmed. 

Street:                                        Thunder Road (between Anderson Road and Ramsayville Road)

Project start date:                   May 24, 2021

Project end date:                    September 24, 2021

Total customers impacted:   16