Starting the week of May 24, Hydro Ottawa is initiating a project that includes the upgrade of a maintenance hole located on Kent Street. This project has an estimated completion date of June 24, 2022. Overall, this work will include:
- lane reductions;
- sidewalk closures; and
- replacement of aging infrastructure.
Below are the details:
Impacted street: Kent Street
Project start date: May 24, 2022
Project end date: June 24, 2022
Contractor on site: Teraflex Limited
Our qualified staff and contractors will conduct this work safely and efficiently, ensuring that any inconvenience is minimal.