Rideau-Vanier - Manhole Upgrade

Start Date:
End Date:

Starting Wednesday, June 17, 2020, in conjunction with the City of Ottawa, East-West Bikeway – Laurier Avenue project, Hydro Ottawa will be upgrading two manholes located on Laurier Avenue East

Residents may notice increased construction presence throughout the duration of the project, including excavation activities and construction vehicles. Traffic control will be implemented when required to ensure that roads and driveways remain accessible and safe to residents.

Planned power interruptions are not expected to occur as a result of this project, and our qualified staff and contractors will conduct this work safely and efficiently, ensuring that any inconvenience is minimal.

Affected street: Laurier Avenue (Nicholas Street to Waller Street)

Project start date: June 17, 2020

Project completion date: July 31, 2020