Bilberry cable replacement project

Bilberry cable replacement project

December 2026 - November 2027

Bilberry cable replacement project is being conducted as an essential requirement to replace aging underground equipment and infrastructure in Orléans West-Innes Ward to ensure long-term reliability in the neighbourhood.

This initiative is more than a single project; we’re prioritizing essential infrastructure replacement projects, such as this one, across our service territory as a core component of Hydro Ottawa's commitment to modernizing our entire electricity grid. These proactive investments ensure we can provide a reliable and sustainable electricity supply for all our customers. 

Why this project is important

Hydro Ottawa equipment in this area is reaching the end of its life cycle. Completing the next phase of the Bilberry cable replacement project is essential so that we can fulfill our commitment to the neighbourhood and meet the long-term capacity and reliability needs of the service area.
 

What this project will include

As part of the Bilberry cable replacement project, the following work will be completed:

  • Excavation and replacement of existing underground infrastructure, including the installation of approximately three switchgears, 29 transformers and 6,000 metres of high-voltage underground cable.
    1,000 metres of new concrete-encased duct bank, 5,000 metres of direct-buried conduit and 12 new cable chambers.
  • To keep the community moving safely while work is underway, residents can expect temporary, localized measures such as short-term traffic controls, brief periods of excavation noise and isolated planned power outages. 

Phase one - December 2026 to May 2027

  • Construction activities will take place along Bilberry Drive and Jeanne d’Arc Boulevard, including the Champlain Street intersection.
  • Construction activities will occur on the City of Ottawa Road Right-of-Way - a legal right of access for Hydro Ottawa to install and maintain its electrical distribution system.
  • This phase of the project is anticipated to result in minimal service disruptions and power outages for customers.
Bilberry Drive cable renewal phase one english

Phase two - April 2027 to November 2027

  • Work will impact residents and businesses along Avignon Court, Chateau Crescent, Decarie Drive and Grenoble Crescent as well as Bilberry Drive and Jeanne d’Arc Boulevard.
  • Some construction activities will occur in residential backyards within designated Hydro Ottawa easements, which are legal rights of access for Hydro Ottawa to install and maintain its electrical distribution system.
  • To ensure our crews and contractors can complete this work safely, this phase is expected to require an increased frequency of planned, isolated power outages.
Bilberry cable replacement project phase two english

Property reinstatement will follow the construction, when the weather permits. Any excavated holes will initially be filled with sand to ensure immediate safety. Final reinstatement, including topsoil and seeding, will be completed according to City of Ottawa guidelines once temperatures and seasonal conditions allow.

As this project advances, customers will be further notified should a planned power outage that impacts their residence or business be required to complete work safely.

How Hydro Ottawa customers will benefit from this project

Once the upgrades are complete, customers will notice a more reliable power supply and higher overall resilience of the electricity system in their area, leading to fewer unplanned power outages. Additionally, utilizing protective piping for the new cables safeguards the efficiency of the electrical grid and significantly increases the lifespan of the cables. These durable encasings are designed to ensure that if issues do occur, faults can be identified and isolated much faster, allowing power to be restored more quickly with fewer overall customers impacted. 
 

Community information sessions

On Wednesday, December 2, 2026, we will host two community information sessions. Impacted residents and businesses will have the opportunity to learn more about the project, including key timelines, but most importantly ask questions and provide feedback. Please join us at one of our sessions: 
   
Virtual information session 
Wednesday, December 2, 2026
12:15 p.m. to 1 p.m.
Register here

You will then receive a confirmation email with the information session access link.

 

In-person information session
Wednesday, December 2, 2026, 7 p.m. to 8 p.m.
Roy G. Hobbs Community Centre
109 Larch Crescent
Orléans, ON K1E 1A2
Please RSVP to [email protected]

Contact

If you have questions about the project please email our Community Relations team at [email protected]
 