Orléans East-Cumberland - Equipment replacement and planned power interruption
Start Date :
End Date :
On September 16, 2026, Hydro Ottawa will be in your neighbourhood to perform planned work. In order to undertake this work safely, a planned power interruption will be required. Below are the details:
Impacted street: St. Pierre Street
Date: September 16, 2026
In case of postponement: September 17, 2026
Time: 9 a.m. to 3 p.m.
Contractors on site: K-Line Group and Westboro Utilities
Our qualified staff and contractors will conduct this work safely and efficiently, ensuring that any inconvenience is minimal.