DER standards, agreements, and other resources

DER standards, agreement & other resources

We’ll provide you with an estimated cost (Service Layout quote) or connection impact assessment and will include the standards relevant to you. You’ll find our other standards listed in the tables below.

Couple reviewing paperwork

Hydro Ottawa standards

The applicable standards referred to in the tables below will be provided at the Service Layout or Connection Impact Assessment, as applicable, and subsequent project stages. The term 'load displacement' in the standards listed below refers to a non-exporting generator; the term 'load displacement' will be removed from these standards in subsequent revisions. Within the technical requirements and standards detailed below, any reference to Micro-generation (10 kW AC or less) effectively encompasses projects up to and including 12 kW. Future revisions of these documents will be updated with this revised threshold.


General standards

No.Document titleRev no.
ECG0002Technical guideline for customer owned emergency backup generation facilities2
ECG0006Distributed energy resource technical requirements5
GCS0008Secondary revenue metering specification6
GDS0018DER service options1
ECG0008Distribution system voltage & power quality5
ECG0023Simplified DER commissioning guide0
ECG0024Standard DER commissioning guide0
 Hydro Ottawa conditions of service 

MCB installation details

No.Document titleRev no.
GCS0048HOL monitoring and control box (MCB) Model B installation with contactor – construction detail1
GCS0051HOL monitoring and control box (MCB) Model B installation with circuit breaker – construction detail0
GCS0054Coming soon 
GCS0055Coming soon 

Metering standards

No.Document titleRev no.
MCS0057DER 120V/240V, 1PH, 3W, ≤200A, and 120V/208Y or 347V/600Y, 3PH, 4W, ≤200A secondary parallel service wiring detail – wiring detail4
MCS0079DER 3PH, 4W, 400A to 600A secondary service construction and wiring detail – construction detail3
MCS0083DER/RES 120V/240V, 1PH, 3W, ≤200A non-exporting or net-metering with single socket base – construction detail4
MCS0084DER/RES 120V/240V, 1PH, 3W, 400A non-exporting or net-metering with ganged meter trough – construction detail5
MCS0085DER/RES 120V/240V, 1PH, 3W, 400A transformer rated service using non-exporting (net-metering) with combination meter socket base – construction detail3
MCS0086DER/RES 120V/240V, 1PH, 3W, 400A to 600A non-exporting (net-metering) with splitter trough – construction detail2
MCS0087DER/COM 120V/240V, 1PH, 3W, 400A to 600A secondary service meter wiring – construction detail2
MCS0088DER/RES 120V/240V, 1PH, 3W, 400A transformer rated service upgrade to combination meter socket base with non-exporting (net-metering) – construction detail1
MCS0089DER/COM 120V/208Y or 347V/600Y, 3PH, 4W, 400A to 600A secondary service with offset meter socket - construction detail3
MCS0090DER 120V/240V, 1PH, 3W, 400A to 600A secondary service with offset meter socket - construction detail2
MCS0097DER 120V/240V, 1PH, 3W, 400A to 600A outdoor enclosure metering pedestal installation with separate instrument transformer cabinet - construction detail1
MCS0098DER 120V/208Y or 347V/600Y, 3PH, 4W, 400A to 600A outdoor enclosure metering pedestal installation with separate instrument transformer cabinet – construction detail0
MCS0102DER 120V/240V, 1PH, 3W, ≤200A, and 120V/208Y or 347V/600Y, 3PH, 4W, ≤200A placement of warning lamacoid and stickers – construction detail0
MCS0104DER 120V/240V, 1PH, 3W, >400A, and 120V/208Y or 347V/600Y, 3PH, 4W, >200A placement of warning lamacoid and stickers – construction detail1
MCS0105AGR/COM/DER/RES minimum clearances in front of revenue metering equipment – construction detail2
MCS0106AGR/COM/DER/RES minimum clearance next to revenue metering equipment – construction detail5

Transfer trip installation details

Not prescribed by a Hydro Ottawa installation detail standard at this time; subject to engineering design and review.