Guide to connecting solar and battery storage


Your guide to connecting 
home solar and battery storage

Solar panels

Thinking about solar or battery storage? Start here.


Considering solar panels, battery storage or both for your home? Before you purchase equipment, there are a few important decisions to make. This guide will help you understand your options, explore available incentives and learn what to expect when connecting these distributed energy resources (DERs) to the Hydro Ottawa grid.

Important: Do not purchase or install your equipment until you have received the required approvals for your project.
 

First, what is a distributed energy resource (DER)?

A distributed energy resource (DER) is a small-scale energy resource located at or near your home that can generate or store electricity behind your meter.

DERs include a broad range of technologies. This guide focuses on the systems most commonly used for residential projects. 
Visit our Types of DERs page for more detailed descriptions.

Solar panels

Rooftop or ground-mounted solar panels generate electricity from sunlight to help power your home.

Battery storage

A battery energy storage system stores electricity so you can use it later. Depending on your system, it may also provide backup power during an outage.

Solar + battery

A solar and battery (hybrid) system can work together to generate and store electricity, giving you more ways to manage when and how you use energy.

Other flexible DERs

Technologies like electric vehicles and smart thermostats are also DERs. They help manage energy demand by adjusting when electricity is used.

Before you buy: 
Understand your project type and grid pathway

Before you purchase or install equipment, start by identifying what you want to add or change at your home. Your DER connection requirements will depend on whether you’re installing a new system, adding battery storage, or modifying an existing system.

What are you planning to install or change?

New solar

You’re installing a new solar PV system without battery storage.

Battery storage

You’re installing a home battery storage system without adding new solar. A battery-only system is not eligible for net metering, but it still requires approval through Hydro Ottawa’s DER connection process.

New solar + battery storage

You’re installing a new solar system paired with a battery storage system. The two systems can work together to generate and store electricity for use in your home.

Adding to or modifying an existing system

You already have a solar or battery system and want to make a change, such as:

  • Adding a battery to an existing solar array
  • Adding solar to an existing battery system
  • Increasing the size or capacity of an existing system
  • Replacing or otherwise modifying existing DER equipment

These projects may have different connection requirements. Hydro Ottawa will review your application and confirm the requirements for your specific project.

solar

If your project includes solar: choose how it will interact with the grid

If you’re installing or modifying a solar system, you’ll need to determine how the system will interact with the electricity grid.

There are two different pathways: non-exporting generation or net metering. Your system can participate in one or the other, but not both.

Not sure which pathway is right for you? Talk to your qualified contractor about your energy goals, proposed system size and available incentives before making a decision.

Available incentives

Once you’ve chosen your approach, explore the programs that may help you get more value from your system. You may be eligible for the Home Renovations Savings Program, GridFlex, or both.

save-on-energy-logo

Home Renovation Savings program

The Home Renovation Savings Program (HRSP) can help eligible Ontario homeowners reduce the upfront cost of installing qualifying home energy improvements. The HRSP incentives described below apply to eligible non-exporting solar projects. The battery incentive is available when eligible battery storage is paired with a new rooftop solar PV system. Program requirements apply.

For eligible new solar + battery projects, you may be able to receive:

  • Solar: Up to $5,000 ($1,000/kW, up to 50 per cent of total costs)
  • Battery energy storage: Up to $5,000 ($300/kWh, up to 50 per cent of total costs)
    = Up to $10,000 total, subject to program requirements and the 50 per cent project-cost cap.
     

Before you start: Your contractor must submit the required pre-installation information and receive written approval before eligible equipment is purchased or installed.

gridflex

You may also be eligible for GridFlex

If you live in an eligible area of Kanata or Stittsville, your battery may be able to do more than help manage energy in your home.

Hydro Ottawa’s GridFlex program rewards eligible customers for helping support local electricity reliability during periods of high demand.

For new home battery storage installations: 

Eligible new home battery storage installations may qualify for a separate and distinct incentive of up to $5,000, calculated at $300/kWh, subject to program requirements. Incentive is capped at 50 per cent of eligible project costs. You do not need to participate in the Home Renovation Savings Program to participate in GridFlex.

Connecting your system to the Hydro Ottawa grid

Once you’ve chosen your system and confirmed the applicable pathway and incentives, you’ll need to apply to Hydro Ottawa’s DER connection process. Every residential DER installation starts with an application to Hydro Ottawa. The specific review, requirements, costs and approvals will depend on the type of system you’re installing or modifying.
 

Select a contractor

Your action

  • Select a qualified contractor and obtain a project quote. Your contractor can help you determine the appropriate system size, equipment and configuration for your home. 
  • For help choosing a solar or battery storage contractor, see our resource guide.
     

Important: Selecting a contractor does not mean you should purchase your equipment. Wait until you have received the required approvals for your project.

 

Apply

Your action

  • Before you buy or install your equipment, submit your DER connection application (Service request form) to Hydro Ottawa.
  • Tell us what you’re proposing to install or modify, including existing DER equipment at your home. We’ll review your application to determine the requirements for safely connecting your proposed system to the grid.

Have the following information ready to apply:

  • A quote from a qualified contractor
  • A close-up photo of your meter and meter base, clearly showing the meter ID number and the conduit entering and exiting the meter
  • A photo showing the entire side of your home where the meter is located
  • A photo of the main breaker on your electrical panel showing the service size
  • A single-line diagram of the proposed system
  • A completed Micro-Distributed Energy Resources (DER) form
Receive your service layout

Hydro Ottawa’s action

  • Hydro Ottawa will review your project and provide a service layout outlining the applicable connection requirements and costs.
  • For standard applications, service layouts are provided within 15 (without site assessment) to 60 days (with site assessment required), and are valid for 90 days.
  • Hydro Ottawa provides up to three complimentary assessments per premise per calendar year.
Install and inspect

Your contractor’s action

  • Once you have the required approvals, your licensed electrical contractor can install your system.
  • Before the system can be energized, the Electrical Safety Authority (ESA) must inspect the installation and issue a certificate of acceptance.
Complete the connection

Your action

  • Submit your ESA Certificate of Acceptance and sign your Hydro Ottawa Micro-Generation Distributed Energy Resource (DER) facility Connection Agreement.

Hydro Ottawa’s action

  • Hydro Ottawa will complete any required meter work, such as installing or upgrading a bi-directional meter, and complete the steps required to energize your connection.

Then your system is ready for use.
 

What will it cost to connect?

Hydro Ottawa charges connection fees for the utility work required to review, connect and energize your DER (see our Connection cost guidance document).

For a standard micro-DER installation, typical Hydro Ottawa connection costs are approximately:

What’s included?

Depending on your project, Hydro Ottawa’s connection costs can include:

  • Site assessment
  • Service layout
  • Meter-related work
  • Grid energization
What’s not included?

You may have additional costs from your contractor or other service providers, including:

  • Your contractor's labour and equipment
  • Building permits
  • ESA inspection fees
  • Electrical panel upgrades
  • Other electrical work required inside your home
     

Ask your contractor for a complete estimate of your project costs.

Ready to get started?

Thinking about solar or battery storage? Start by understanding your options, incentives and connection requirements.

Your next steps:

Have questions?

For more information about connecting a solar or battery storage system to the Hydro Ottawa grid, contact us at [email protected] or 613-738-5499 ext 7312 or explore our DER resources.

For more information on incentives (GridFlex or HRSP), fill out our GridFlex contact form 
or phone us at 1-844-417-3482.