Piperville Municipal Transformer Station

Piperville municipal transformer station

March 2020 - September 2026

To ensure Ottawa’s eastern region has the power to grow, Hydro Ottawa has initiated a Class Environmental Assessment (Class EA) study for the construction of a new 27.6kV municipal transformer station in the southeast end of the city of Ottawa.

What will this project include?

The Piperville Municipal Transformer Station project proposes:

  • to construct a new 27.6kV municipal transformer station (MTS) at the intersection of Piperville Road and Farmers Way (located on the west side of Highway 417); and
  • to connect the new power station to Hydro One’s existing 230kV transmission line, also located on the west side of Highway 417.
Piperville map

As part of our sustainability commitments, Hydro Ottawa intends to develop Piperville as a low-carbon substation.

We are currently undertaking a full project review of the station’s construction, including an innovative design, procurement and construction techniques that include using lower Global Warming Potential (GWP) materials, and equipment that will address embodied carbon associated with the construction and operation of the substation.

Why we are moving forward with this project

The need for new facilities was identified through the Integrated Regional Resource Plan (IRRP) for the Ottawa area. Released in March 2020, the IRRP is a twenty-year plan that has been developed by a regional planning working group consisting of the Independent Electricity System Operator (IESO), Hydro Ottawa and Hydro One.

This project will support projected growth in electricity demand for the area and provide redundancy to our system in the event of future extreme weather events. The Piperville Municipal Transformer Station is one of many future-planning projects we are spearheading to make our electricity system as resilient, and as sustainable, as possible.  

The existing Hydro Ottawa station in the area does not have the capacity to supply anticipated future demand in this part of the city.

Hydro Ottawa Piperville vertical timeline

Final environmental study report

January 29th, 2024

This Final Environmental Study Report describes the technical and environmental studies undertaken on behalf of Hydro Ottawa Limited for this project.

Resources from community information session 3

Resources from community information session 2

Resources from community information session 1 