Somerset Ward - Infrastructure installation project

Start Date:
End Date:

Starting March 16, 2026, Hydro Ottawa will begin the installation of a new concrete-encased duct bank in front of 969 Somerset Street West. This critical infrastructure is required to house underground cabling and is essential for maintaining the long-term stability of the electrical distribution system in the area. The project has an estimated completion date of March 27, 2026.

 

Impacted street: Somerset Street West

Project start date: March 16, 2026

Project end date: March 27, 2026

Contractor on site: Lourenco & Botelho Inc.

 

Our qualified staff and contractors will conduct this work safely and efficiently, ensuring that any inconvenience is minimal.