Starting January 27, 2025, Hydro Ottawa is upgrading a maintenance hole located on Bank Street between James Street and Frank Street. This project has an estimated completion date of March 7, 2025.
Overall, this work will include:
- electrical equipment infrastructure upgrades;
- road closure on Florence Street at the intersection of Bank Street and Florence Street; and
- sidewalk closure at site.
Impacted streets: Bank Street and Florence Street
Project start date: January 27, 2025
Project end date: March 7, 2025
Contractor on site: Bradley Kelly Construction
Our qualified staff and contractors will conduct this work safely and efficiently, ensuring minimal inconvenience.