Barrhaven East Ward - Critical pole replacement project

Start Date:
End Date:

Starting September 29, 2025, Hydro Ottawa will be replacing critical hydro poles and equipment on Woodroffe Avenue at Queensbury Drive. We estimate that this project will be completed by October 17, 2025. 

 

Impacted Street: Woodroffe Avenue at Queensbury Drive

Project Start Date: September 29, 2025

Project End Date: October 17, 2025

Contractor on site: Bradley Kelly Construction Ltd.

 

Our qualified staff and contractors will conduct this work safely and efficiently, ensuring minimal inconvenience.